Tenant improvement allowance in Los Angeles

What the landlord puts toward your build out, and what happens past it

General education, not legal, tax or financial advice. I am not a licensed real estate agent or broker. My California salesperson license is in progress. For a real lease, use a licensed broker and an attorney.
Direct answer

A tenant improvement allowance is money the landlord agrees to put toward building out your space, usually quoted per square foot and set in the lease or a work letter. It is rarely free: landlords weigh it against rent, term and other concessions. If construction costs more than the allowance, the tenant usually pays the difference, either up front or added to rent over the term.

How it is quoted

The allowance is usually stated in dollars per square foot, and the lease says which square feet, rentable or usable. In the made up example below, $40 a foot on 3,000 rentable square feet is $120,000. The rent per square foot guide explains the difference between rentable and usable.

Two other arrangements are common. In a turnkey deal the landlord delivers the space finished to an agreed plan. In an as is deal the landlord does no work and delivers the space in its current condition; some as is deals still include an allowance for the tenant's own build out, and some include none.

What it usually covers

The work letter says what the allowance can pay for. Construction itself, the hard costs, is almost always in. Soft costs are often capped or left out:

  • Architecture and space planning
  • Engineering and permits
  • Project management fees
  • Cabling, furniture and moving

If the allowance cannot pay for cabling, furniture or moving, budget for them separately.

When the build costs more

The difference is usually the tenant's. It gets paid one of two ways: in cash during construction, or amortized, where the landlord funds it and adds a monthly payment, with interest, to rent over the term. If it is amortized, the lease should state the rate, the period, and what happens to the unpaid balance if the lease ends early.

What to settle in the work letter

  • Who hires the contractor, and who approves the plans
  • How and when the allowance is paid out, and what paperwork, such as lien releases, comes first
  • Whether unused allowance can go toward rent or other costs, or is lost
  • A deadline to use the allowance
  • Who pays for delays, and whether rent starts on a fixed date or when the work is done
  • Who owns the improvements at the end, and whether you have to remove them

California: the CASp line

For commercial property offered to businesses open to the public, California Civil Code 1938 requires the lease to state whether the premises have been inspected by a Certified Access Specialist (CASp). If a CASp report notes access violations, the owner or lessor is presumed responsible for fixing them unless the parties agree otherwise. Where the premises have no disability access inspection certificate, the lease has to include wording set by the statute: the landlord may not stop the tenant from getting a CASp inspection on request, and the parties will agree on the timing, who pays the inspection fee, and who pays for repairs within the premises. Settle that in the work letter, because access work and a build out often touch the same doors, counters and restrooms.

Worked example: an allowance and an overage

Made up numbers: 3,000 rentable square feet on a five year lease.

ItemAmountMath
Allowance at $40 a foot$120,0003,000 x $40
Build out cost$165,000
Overage$45,000$165,000 minus $120,000
Overage amortized over 60 months at 8 percent$912.44 a monthStandard loan payment formula
Added to rentAbout $0.30 a foot a month$912.44 / 3,000

Over the term that is $54,746 in payments for $45,000 of work, and the difference is interest. Paying cash avoids the interest but takes $45,000 out of the business before you open.

Questions

Frequently asked questions

What is a tenant improvement (TI) allowance?

Money the landlord puts toward building out a tenant's space, set in the lease or work letter and usually quoted per square foot.

Is there a Los Angeles or California rule for how big the allowance is?

No. The amount is a negotiated lease term, and nothing in the statute cited here sets it. California law does speak to access inspections (the CASp section above), so settle that in the same work letter.

Is the allowance negotiable?

Yes. It gets traded against rent, free rent, term length and who manages construction, so compare offers on total cost over the term, not the allowance alone.

What if I do not use the whole allowance?

The lease decides. Some let unused allowance go toward rent or other costs, and many do not. Settle it before signing.

Who owns the improvements when the lease ends?

The lease decides that too. Often they stay with the building, and some leases require the tenant to remove specialized work and restore the space.

Can the allowance pay for furniture?

Only if the work letter says so. Furniture, cabling and moving are often excluded or capped.